A vendor tells you the app is '90% done.' Six weeks later, it's still '90% done.' If that sounds familiar, you're in good company. The '90% done' claim is the most common sentence in outsourced software, and it is almost never something you can verify. Progress on an app isn't a straight line, and a percentage hides everything that matters: what works, what doesn't, and what hasn't been started.
The good news is that you don't need to read code to find out where you stand. You just need to stop accepting a number and start asking for evidence. Here is how to pressure-test a '90% done' claim, whether you're evaluating a dev studio, trying to unstick a stalled build, or deciding between outsourcing and hiring in-house.
Why '90% done' means almost nothing
Percentages measure effort spent or screens drawn, not risk remaining. The last stretch of a software project is where the unglamorous work lives: payments that fail in odd ways, login edge cases, slow screens on older phones, app store review, data migrations, security fixes. A build can look finished in a demo and still be months from launch, because the demo only shows the happy path.
A percentage is also impossible to argue with. If you say 'that feels slower than 90%,' there's no fact to point to. Specific evidence changes that. It turns a conversation about feelings into a conversation about things you can see and count.
The five questions to ask
- Can I see it running right now, on a real device? Not a slideshow, not screenshots, not a video recorded last month. Ask for a build you can install on your own phone or open in your own browser today. If the vendor can't produce one within a day or two, that tells you something. A team that ships regularly always has a working build.
- Which features are not built yet? Ask for a written list of everything in the original scope, each marked as done, partly done, or not started. A candid team will hand this over without fuss. A vague answer like 'just some polish left' usually means the list is longer than they want to admit.
- How many known bugs are open, and how serious are they? Every real project has a bug list. Ask to see it. You aren't looking for zero. You're looking for a team that tracks bugs honestly, sorts them by severity (crashes and data loss first), and can tell you which ones block launch. If there is no bug list at all, nobody is testing.
- What happens when something goes wrong? Ask what the app does when the internet drops, a payment fails, or a user enters something unexpected. Also ask about security, especially if the app uses AI features or handles personal data. Teams that have built production software answer these questions quickly and specifically. Teams that built a prototype tend to go quiet.
- Who owns the code, and could another team pick it up tomorrow? Ask where the source code lives, whether you have access to it, and whether there is documentation. If the work is only 'done' inside one person's laptop, you're not 90% of the way to anything. You're dependent on them.
What good answers look like
Good answers are boring and concrete. 'Here's the build, here's the list, here are the 14 open bugs and the three that block launch.' Notice there's nothing impressive in that. It's simply checkable. Trust follows from being able to check.
What warning signs look like
- The build is 'being fixed' every time you ask to see it.
- The remaining work is described in adjectives ('polish,' 'final touches') instead of a list.
- The percentage goes up slowly, or sits still, while the deadline keeps moving.
- You can only talk to a project manager, never to the engineer doing the work.
What to do if the answers are bad
Don't panic, and don't assume bad faith. Most inflated progress claims come from optimism, not dishonesty. But you do need an independent read on where things stand. A short code audit by someone with no stake in the project can tell you what exists, what's solid, and what would have to be rewritten. That's often a small cost compared with another quarter spent on a build that was never going to finish.
From there, the decision is much easier. You can keep your current team with clearer milestones and weekly demos, bring in a second team to finish the work, or rebuild the weak parts. Whichever you choose, set the same rule going forward: progress is reported as a running build and a list, never as a percentage.
A closing note
At orithLabs, we're two founders, and you talk directly to the engineers writing your code. We'd rather hand you an honest list of what's built and what isn't than a comforting number, and we apply the same standard to our own shipped apps, Crumb Count and Kompete. If you're sitting on a '90% done' app and aren't sure what that means, we're happy to take a look and tell you plainly what we see.