You're three weeks into the build. You ask your dev shop to add a "forgot password" flow you assumed was included. The answer is a change request with a new estimate, and you can't argue with it, because the contract never said it was included. The proposal said "user authentication," and the change request clause said anything outside the agreed scope would be "billed separately at prevailing rates." Nobody lied to you. The contract was simply written so that every gap would be billed to you.

Most budget overruns we see in outsourced software projects start there, not in bad code. A single clause decides whether a quote is a ceiling or just an opening bid. Here's how that clause tends to be written, what the vague parts cost you in practice, and the wording we use instead, so you can redline a proposal before you sign it.

The vague wording we keep seeing in dev contracts

When founders bring us a stalled project for a code audit, we often ask for the original agreement too. The same phrases come up again and again:

  • "Includes reasonable revisions." Reasonable according to whom? This usually means the vendor decides when you've used up your revisions, and you find out from an invoice.
  • "Minor changes will be accommodated." No definition of minor. Changing a button label is minor. Adding a field to a form sounds minor, but it can touch the database, the API, validation, the admin dashboard and both mobile apps.
  • "Additional work billed at prevailing rates." The rate isn't written down, and neither is the process for approving the work. Sometimes the work is already done before you hear the price.
  • "Scope may evolve as the project progresses." True of every project, and useless as a contract term. It gives no rule for who pays when scope changes.
  • "Bug fixes included during the warranty period." This sounds protective until the vendor calls missing behavior a "new requirement" rather than a bug. Without written acceptance criteria, there's nothing to settle that argument.

Each of these looks harmless on its own. Together they move all of the risk of an incomplete spec onto you, and every spec is incomplete. That's the nature of building something new, especially in MVP development, where you learn what users need only after they touch it.

How "reasonable revisions" turns into an open-ended invoice

The pattern is predictable. The proposal describes features at headline level: "user profiles," "payments," "admin panel." The price is fixed against that list. Then the actual work starts, and every detail the headline didn't settle becomes a negotiation. Does "payments" include refunds? Partial refunds? Failed-payment retries? Invoices emailed to the customer?

Under a vague change request clause, each of those questions is a chance to bill again. The vendor isn't necessarily acting in bad faith. They priced the narrowest reading of the feature because that's how they won the bid. But you pay for the gap between what you meant and what the contract says, and you usually find out about it in small amounts over months, after you've invested too much to switch vendors.

Founders often compare a freelancer and an agency on day rate or total quote. Comparing their change request clauses is more useful. A lower quote with an open-ended clause often ends up costing more than a higher quote with a tight one.

The change request clause wording we use

This is the structure we put in our own agreements. You don't need to copy it word for word, but if a proposal you're reviewing is missing any of these parts, that's where to redline.

  1. Scope is defined by acceptance criteria, not feature names. Each feature lists what "done" means in testable terms, for example: "User can reset password via an emailed link that expires after a set period." If it's in the criteria, it's included. If it isn't, it's a change. Neither side has to guess.
  2. A defect is anything that fails the agreed criteria, and fixing it is free. This is the counterpart to the line above. The vendor can't relabel broken behavior as new scope.
  3. No change work starts without written approval. Every change request gets a written impact note covering the added time, added cost, which parts of the system it touches (backend, mobile, admin dashboard), and whether it moves the delivery date. Work starts only after you approve that note in writing. Nothing is billed retroactively.
  4. The rate is in the contract. Not "prevailing rates," but the actual rate, written into the agreement, so every estimate can be checked.
  5. "Revision" has a defined meaning. In our wording, a revision changes copy, layout or styling on an already-agreed screen without adding new data, states or integrations. Anything that adds those is a change request, priced as above.
  6. There's a threshold that forces a conversation. If approved changes add up past an agreed share of the original budget, both sides pause and re-plan the remaining scope. This stops a series of small, sensible approvals from quietly doubling the project.
  7. Either side can raise a change. If we find mid-build that something in the spec won't work as written, we use the same process. You see the trade-off before we act on it.

The clause doesn't make changes disappear. Good projects change, because you learn things. What it does is make each change visible, priced and approved before it costs you anything, which is all a founder needs to manage a budget.

A quick redline checklist

  • Is "done" defined per feature, or just named?
  • Is the hourly or daily rate written into the contract?
  • Does change work need your written approval before it starts?
  • Is the difference between a defect and a change spelled out?
  • Is there a cap or re-planning trigger on total changes?

If you answer no to two or more of these, treat the quoted price as a floor rather than a ceiling.

Before you sign: questions to ask any software consultancy

Ask the vendor to walk you through a recent change request on a real project: who raised it, how it was estimated, and how long approval took. A team with a working process can answer in a couple of minutes. A team without one will talk about "flexibility" and "partnership." Also ask who writes the acceptance criteria. If the answer is "we'll figure it out as we go," it will be figured out on your invoice.

At orithLabs, this clause exists because we'd rather spend an extra hour agreeing on scope up front than have that argument in month three. It's the same approach we used on Crumb Count and Kompete: say exactly what's being built, and say clearly what isn't. If you have a proposal on your desk and want a second pair of eyes on the scope wording, or a stalled build where the contract is part of the problem, we're happy to look at it with you.