"We're 80% done." If you've hired a development team, you've probably heard some version of that sentence in a Friday email, and then heard it again four weeks later. Percent-complete is the most common line in dev shop progress reports, and it's close to meaningless: nobody can check it, and the last 20% routinely takes as long as the first 80%.
A weekly update written in paragraphs of effort ("the team made good progress on the onboarding flow") tells you that people were busy. It doesn't tell you whether the project is healthy. Below are the five numbers orithLabs puts in front of clients instead. Each one is something a non-technical person can verify without reading code.
Why dev shop progress reports drift away from reality
Nobody has to be lying for this to happen. Status writing rewards optimism. Work that is "in progress" can stay in progress for weeks. Risks get softened because nobody wants to alarm a client over something that might resolve. Scope creeps in as small favors that never make it into the report.
The result is that the first honest signal often arrives in month four, when a demo doesn't work or a deadline quietly moves. By then you've spent most of the budget. The fix isn't a longer report. It's a shorter one made of things that can't be argued with.
The five numbers
1. Working builds shipped
Not features "completed" by the team's own definition, but builds you can install or open and use yourself. For a mobile app, that means a build on your phone through TestFlight or an Android test track. For a web backend or admin dashboard, it means a link you can click.
Count them weekly. If week one and week two both show zero, that's a finding. A healthy project produces something runnable early, even if it's ugly. Something you can tap beats a slide deck every time.
2. Open risks
A list of things that could hurt the project, each with an owner and a date. Examples: a third-party API with unclear limits, an app store review requirement we haven't tested against, a payment integration that depends on an account you haven't created yet.
The number matters less than the direction and the honesty. A report with zero risks in week three isn't reassuring; it means nobody is looking. Risks that stay open for weeks without a plan are the ones that become month-four surprises.
3. Decisions waiting on you
This one is uncomfortable for us, because it points at the client. But a large share of stalled projects stall on unanswered questions: which payment provider, which approval flow, which copy goes on the screen. We list every decision we need from you, how long it has been waiting, and what it blocks.
It keeps both sides honest. If the number is climbing, the delay is on your desk. If it's zero and the project is still slow, the delay is on ours, and you know where to push.
4. Days since last deployable build
Take the date of the most recent version that could be released if you said go, and count the days since. This is the closest thing to a heartbeat a software project has.
When the number stays in the single digits, integration problems are being found and fixed continuously. When it creeps to three or four weeks, the team is usually building in a branch somewhere and hoping the pieces fit together later. That's how technical debt piles up unseen, and how "almost done" turns into months. Teams with solid CI/CD pipelines have a naturally low number here, which is one reason we set that up in week one.
5. Scope changes
Every addition, removal, or "small tweak" gets logged with its effect on timeline and cost, whether the request came from you or from us discovering something. Scope change is the most common reason an MVP development project overruns, and it's rarely one big decision. It's a dozen small yeses.
Seeing the running tally lets you choose deliberately. Sometimes the new feature is worth the delay. The point is that you chose it, rather than discovering it in an invoice.
How to use these in week two
You don't need to understand the code to read this. Ask any team you're working with, ours or anyone's, for these five items every week:
- Zero working builds by the end of week two: ask what's blocking a first runnable version.
- Risks that never change: ask what's being done about each one, and by when.
- Decisions aging past a week: clear them yourself, today.
- Days since deployable build above ten: ask why, and what would shorten it.
- Scope changes nobody remembers agreeing to: ask for the log.
If a team can't produce these numbers, that tells you something too. It usually means they aren't tracking them, which means nobody is managing the risk they describe. The same questions are useful whether you're comparing a dev studio against a freelancer, evaluating outsourcing against an in-house hire, or trying to work out why a stalled build stopped moving.
One caveat: these numbers don't guarantee success. They make problems visible early, when fixing them is cheap, and that's the whole job of reporting.
Closing thought
At orithLabs, two founders build and ship the work, so you talk to the engineers directly and the five numbers come straight from the people writing the code. If you're weighing a build, or you have one that's gone quiet and you'd like a second opinion on where it stands, we're happy to look at it and tell you plainly what we see.