Two sentences in a Slack message can cost a day, or a month. "Can we add Apple login?" and "Can we let users split the payment?" read as the same size of request. They aren't even close.
Software scope creep is the quiet reason many builds go over budget. It rarely comes from bad faith. It comes from smart founders learning something mid-project and wanting to act on it. The problem is that nobody has told them which changes are cheap and which ones reach into the foundations.
We won't publish dollar figures here. Real cost depends on your codebase, your team and your rates, and a number out of context would mislead you. Instead, here are seven change requests of the kind we see on mobile and web builds, sorted by how much they actually hurt, and why.
The cheap ones: changes that sit on top of the system
1. Wording, colour and layout tweaks
Cost: small. These touch only the surface. The risk is volume: fifty small tweaks in one week add up to real hours. Batch them into a single list and they get done in one pass.
2. A new filter or export on the admin dashboard
Cost: small to moderate. If the data already exists, an admin dashboard filter or CSV export is mostly display work. The cost climbs only if the data you want to filter on isn't being stored yet. That is a different request (see number 6).
3. Adding Google or Apple sign-in
Cost: moderate. The button is the easy part. The hard part is what happens when someone signs up with email, then later taps "Sign in with Apple" using a different address. Do you merge the accounts or create a duplicate? Someone has to decide, build it and test it on real devices. Also, Apple generally requires its own sign-in option if you offer other social logins in an iOS app, so this one is often non-negotiable anyway. Ask for it early and it's a planned feature. Ask for it a week before launch and it's a delay.
The ones that blow up timelines
4. The "quick" extra screen
Cost: small to large, and you can't tell from the outside. A screen is never just a screen. It needs data from somewhere, a loading state, an empty state, an error state, and behaviour on slow networks. If the data already comes from the backend, it's a modest job. If it needs a new API endpoint, a new database table and permission rules, you've commissioned a small feature and called it a screen. The honest answer to "how long for one more screen?" is usually "let us check what feeds it."
5. Push notifications
Cost: moderate to large. iOS and Android handle permissions differently, delivery is not guaranteed, and someone has to decide who gets what, when, and how to stop it from becoming spam. The code is one part. The rules around it are the rest.
6. A payments tweak
Cost: large relative to how it sounds. "Let customers add a tip," "apply a discount code," "allow partial refunds." Each sounds like one field. Each changes how money moves, which means changes to how totals are calculated, how refunds reverse them, what your finance records show, and what happens when a payment fails halfway. Payment changes need more testing per line of code than almost anything else, and cutting corners there is how you get real customers charged wrongly. We treat this category conservatively on purpose.
7. A change to how the data is structured
Cost: the largest. Example: "Actually, a user should be able to belong to several teams, not just one." That sentence rewrites an assumption that dozens of screens and rules were built on. It means changing the database design, migrating existing data safely, and revisiting every place the old assumption lived. Done in week two, it's an afternoon of redesign. Done after launch, it's a project of its own.
How to word a change request so it stays cheap
Nearly every expensive change has one thing in common: it changes a rule, not just a view. You can spot these by asking whether the request alters who can do what, how money moves, or how records relate to each other. If yes, expect it to cost more than it sounds.
Then word it for the engineer, not for yourself:
- Describe the outcome, not the screen. "Customers should be able to pay for a friend's order" gives your developer room to find the cheapest route. "Add a button here" doesn't.
- Say what's driving it. A deadline, a customer complaint and a hunch each deserve different answers.
- Ask for the trade-off, not just the price. "What does this push out, and what's the cheapest version?" gets you options instead of a number.
- Batch small asks. One weekly list beats twenty interruptions.
- Flag the rule-changers early. Anything touching accounts, payments or data structure belongs in the first planning conversation, not the final stretch.
A good development partner should also be telling you this, not hiding it. If every change request gets an instant "sure, no problem," that is a warning sign. It usually means the real cost shows up later as a bug or an invoice.
What to do with this
You don't need to become technical to control scope. You need a short habit: before approving a change, ask which of the three buckets it falls in (surface, new data, or new rule), and ask for the estimate with that in mind. Founders who do this tend to ship sooner and argue less about invoices.
At orithLabs, we work this way on every build: you talk directly to the two engineers doing the work, change requests get sized in plain language before anyone starts, and we tell you when a "quick" ask isn't quick. If you have a change list sitting on your desk and aren't sure what it really involves, we're happy to look at it and tell you honestly which items are cheap.